求翻译:As part of a water storage scheme for a British Regional Water Authority to regulate flows in the River Derwent in England, a 1225 m long, 35 m high zone earth filled embankment was being constructed from 1981 to 1984. The Carsington Dam would be one of the largest earth-fill dams in Britain. The scheme was designed so是什么意思?

待解决 悬赏分:1 - 离问题结束还有
As part of a water storage scheme for a British Regional Water Authority to regulate flows in the River Derwent in England, a 1225 m long, 35 m high zone earth filled embankment was being constructed from 1981 to 1984. The Carsington Dam would be one of the largest earth-fill dams in Britain. The scheme was designed so
问题补充:

  • 匿名
2013-05-23 12:21:38
作为英国地区水务局来调节的德文特河在英格兰,1225米长流之水存储方案的一部分35米,高区土填路基被修建1981年至1984年。该carsington大坝将是英国最大的填土水坝之一。该计划的目的是使水将通过一个10公里长的隧道冬季期间转移并储存在其中有35万立方米的估计能力的水库。将水从水库被释放时,在河的水位很低。
  • 匿名
2013-05-23 12:23:18
作为英国地方水利局的水存贮计划一部分能调控流程在河Derwent在英国,长1225个的m, 35 m高区域地球被填装的堤防被修建从1981年到1984年。Carsington水坝是其中一个最大的地球积土水坝在英国。计划被设计了,以便水通过一个10 km长隧道在有35百万个cu m估计的容量的水库将被调在冬天期间并且被存放了。
  • 匿名
2013-05-23 12:24:58
作为水存贮计划一部分为了英国的地方水利局能调控流程在河Derwent在英国, 1225 m长, 35 m高区域地球被填装的堤防被修建从1981年到1984年。 Carsington水坝是一个最大地球填装水坝在英国。 计划被设计了,以便水通过一个10公里长隧道在有35百万cu m估计的容量的水库将被牵制在冬天期间并且被存放了。 当水平面在河低,水从水库将被发布。
  • 匿名
2013-05-23 12:26:38
作为一个英国区域供水管理局,以规管流动的河德文在英格兰,1225 m 长,水存储计划的部分 35 m 高区填土路堤修筑时从 1981 年到 1984 年。Carsington 大坝将在英国最大的填土水坝之一。该计划被设计为水将会通过一条 10 公里长隧道在冬天期间挪用和存储在水库有 3500 万立方米 m.估计的容量水将从被释放,水库在河中的水级别低的时候。
  • 匿名
2013-05-23 12:28:18
作为用于调整的一种英国区域的水权力的一项水存储计划的一部分在英格兰流动乘 River Derwent, 1225 米长, 35 米高地区的地球填充筑堤由 1981 至 1984 被在建造。Carsington 障碍会是在不列颠的最大地球填充的障碍之一。计划被设计,以便水会被在冬天期间通过 10 公里长的隧道转向和存储在有三千五百万 cu m 的一种被估计的能力的水库。水在河的水位是低的时会从水库被发布。
 
 