求翻译:   Suppose that project management is as neutral about risk preferences, namelyβ→0.5,so each procedure time can be calculated respectively, for example, the first procedure’ s most likely time was =6+0.5*(8-6)=7(days). By analogy, the others corresponding periods of each working procedure were as =13.5(days), =18(days)是什么意思?

待解决 悬赏分:1 - 离问题结束还有
   Suppose that project management is as neutral about risk preferences, namelyβ→0.5,so each procedure time can be calculated respectively, for example, the first procedure’ s most likely time was =6+0.5*(8-6)=7(days). By analogy, the others corresponding periods of each working procedure were as =13.5(days), =18(days)
问题补充:

  • 匿名
2013-05-23 12:21:38
假设项目管理是中性对风险的偏好,namelyβ→0.5,所以每道工序时间可分别进行计算,例如,第一个过程是最有可能的时间是= 6 +0.5 *(8-6)= 7(天)。通过类比,相应的每道工序的期间,其他都是为= 13.5(天)= 18(天)= 27.5(天)= 31(天)= 27.5(天)= 26(天),T = 33.5(天)= 16.5(天)。
  • 匿名
2013-05-23 12:23:18
假设项目管理是作为关于风险偏好, namelyβ→0.5的中性,因此每做法时刻可以分别被计算,例如,第一procedure s很可能次是=6+0.5* (8-6) =7 (几天)。由比喻,其他每项工作程序的同期是作为=13.5 (几天), =18 (几天), =27.5 (几天), =31 (几天), =27.5 (几天), =26 (几天), t=33.5 (几天), =16.5 (几天)。
  • 匿名
2013-05-23 12:24:58
正在翻译,请等待...
  • 匿名
2013-05-23 12:26:38
假设项目管理是风险偏好,namelyβ→0.5,是中性的所以为的示例中,第一个过程可以分别计算每个程序时间 ' s 最可能的时间是 = 6+0.5*(8-6)=7(days)。通过类比,其他相应期间的每一道工序都 = 13.5(days)) = 18(days) = 27.5(days) = 31(days),= 27.5(days),= 26(days),t=33.5(days),= 16.5(days)。