2013-05-23 12:21
求翻译:The surge arresters and support structure shall be qualified according to the requirements of IEEE Std 693-2005. The surge arresters and support shall meet the requirements of the high seismic qualification level. (Structure height and information discussed in item d) of 4.2 must be included if the support structure is是什么意思? 待解决
悬赏分:1
- 离问题结束还有
The surge arresters and support structure shall be qualified according to the requirements of IEEE Std 693-2005. The surge arresters and support shall meet the requirements of the high seismic qualification level. (Structure height and information discussed in item d) of 4.2 must be included if the support structure is
问题补充: |
|
2013-05-23 12:21:38
避雷器和支撑结构应根据IEEE标准693-2005的要求才算合格。
|
|
2013-05-23 12:23:18
浪涌逮捕和支持结构根据IEEE将合格Std 693-2005的要求。浪涌逮捕和支持将符合高的地震资格水平的要求。(在项目和信息谈论的结构高度d) 4.2一定是包括的,如果需要支持结构。实验计划在35个日历合同裁定书内将递交,并且测试在75个日历合同裁定书内将完成。
|
|
2013-05-23 12:24:58
浪涌逮捕和支持结构根据IEEE将具有资格Std 693-2005的要求。 浪涌逮捕和支持将符合高的地震资格水平的要求。 (如果需要,在项目和信息谈论的) 结构高度d 4.2一定是包括的支持结构。 实验计划将递交在35个日历合同裁定书内,并且测试将完成在75个日历合同裁定书内。 报告将递交在21个日历内在测试以后是完全的。
|
|
2013-05-23 12:26:38
电涌放电器和支撑结构应符合 IEEE Std 693-2005 要求。电涌放电器和支持应满足高抗震鉴定水平。(结构高度和 d) 项所述的信息) 的 4.2 必须被包括在内如果支持结构是必需的。批出合约,35 个日历日内须提交的测试计划和测试须批出合约的 75 个日历日内完成。报告应在完成测试后 21 个日历日内提交。
|
|
2013-05-23 12:28:18
巨涌停机装置和支持结构将被根据 IEEE 标准的要求具有资格 693-2005。巨涌停机装置和支持将高地震资格水平的符合要求。( 结构顶点和信息讨论在条款 d 中 )4.2 中必须被包括如果支持结构需要。测试计划将在合同的奖的 35 日历日内被提交,以及测试将在合同的奖的 75 日历日内完成。报告将在 21 内被提交在测试之后几天的日历是完整的。
|