求翻译:Comply with P&P on Supplier Invitation Requirements ? According to HWPL Tendering and Quotation P&P, the user team and independent team should propose an equal number of suppliers to be invited. However, currently the proportion of suppliers proposed by either party was not properly documented and there was no evidence是什么意思?

待解决 悬赏分:1 - 离问题结束还有
Comply with P&P on Supplier Invitation Requirements ? According to HWPL Tendering and Quotation P&P, the user team and independent team should propose an equal number of suppliers to be invited. However, currently the proportion of suppliers proposed by either party was not properly documented and there was no evidence
问题补充:

  • 匿名
2013-05-23 12:21:38
与P&P对供应商的要求邀请符合?根据HWPL招标和报价P&P ,用户团队和独立的团队应该提出同等数量的供应商被邀请。
  • 匿名
2013-05-23 12:23:18
遵守P&P供应商邀请上要求是什么?根据hwpl招标和报价P&P,用户小组和独立的小组应提出一个相同数量的供应商参加。 然而,目前这一比例的建议供货商的任何一方未正确记录,也没有证据表明,这样的政策是在现有招标和报价。
  • 匿名
2013-05-23 12:24:58
依从P&P在供应商邀请要求? 根据HWPL招标和引文P&P,用户队和独立队应该提出供应商的一个相等的数字将被邀请。 然而,任一个团体提议的供应商的比例未适当地当前被提供,并且没有证据这样政策在现有的招标和引文做法被执行了。 实时性继续采取的行动卓著的R&M生产顺序和更新工作进展? 生产顺序记数器由R&M队手工维护接着和监测工作进展。 然而,工作进展总不实时性更新。 例如,一个生产顺序从2014年3月实际上完成了,但仍然以状态“等待的材料”自我们的审计日期。
  • 匿名
2013-05-23 12:26:38
遵守供应商邀请要求 P & P? HWPL 投标、 报价及 P 用户团队和独立的团队应该提出供应商邀请的同等数目。然而,目前的供应商比例提出要么方没有正确记录和有现有的招投标和报价过程中,没有证据证明实行这种政策。及时按照了优秀 R & M 工作订单和更新工作进度? R & M 团队跟进和监察工作进度由手动维护工作订单的登记册。但是,工作进展不总是及时更新。例如,工作顺序从 2014 年 3 月实际完成但仍与地位"挂起材料"日期为我们的审计。